高新工程项目研制过程中的最优评审点设计
引用本文:王晶,席阳,韩勇.高新工程项目研制过程中的最优评审点设计[J].北京航空航天大学学报,2005,31(5):556-560.
作者姓名:王晶  席阳  韩勇
作者单位:1. 北京航空航天大学 经济管理学院, 北京 100083;
2. 北京科技大学 管理学院, 北京 100083;
3. 空军装备部?订货部, 北京 100843
基金项目:航空基础科学基金;03J51054;
摘    要:高新工程研制过程普遍采用了并行工程的方法,虽然大幅度地缩短了工期,但是其风险较高.通过分析并行工程实施风险产生的原因,构建了并行工程实施过程的一般风险模型,指出最优决策点位于"时间-风险"关系曲线与"风险-技术成熟度"关系曲线的交汇点,给出了高新工程项目研制过程中的风险分类.提出设置有效的评审点是降低实施并行工程总体风险的可行方法,并设计了最优评审点的确定方法,利用技术风险因子、进度风险因子和并行风险因子求出各项任务风险大小,再加和求出项目整体风险.通过实例说明了评审点的最优设计可以有效降低项目的整体风险.

关 键 词:最优设计  风险  并行工程  最优评审点
文章编号:1001-5965(2005)05-0556-05
收稿时间:2003-11-25
修稿时间:2003年11月25日

Optimized evaluation point designing for R&D project
Wang Jing,XI Yang,Han Yong.Optimized evaluation point designing for R&D project[J].Journal of Beijing University of Aeronautics and Astronautics,2005,31(5):556-560.
Authors:Wang Jing  XI Yang  Han Yong
Institution:1. School of Economics and Management, Beijing University of Aeronautics and Astronautics, Beijing 100083, China;
2. School of Management, Beijing University of Science and Technology, Beijing 100083, China;
3. Ordering Office of Equipping Department of the Air Force, Beijing 100843, China
Abstract:Having been widely adopted in the management of research and development (R&;D) projects, concurrent engineering can largely shorten the time limits for projects, however, its risk is higher. A risk model of implementing concurrent engineering was built. The optimum decision point is exactly the intersection between the "risk versus technological-maturity" relation curve and the "time versus risk" relation curve, and the classification of risks in R&;D projects was proposed. Setting valid evaluation point is effective to control and reduce the risks, and a method to identify the optimized evaluation points was designed. In the method, the risks of each task can be determined by technological risk factors, scheduling risk factors and parallel risk factors, and then the overall risk of the project can be determined by the summation of all the risk values. A numerical example was used to demonstrate that the overall risk of R&;D projects can be effectively reduced through the optimized evaluation point designing.
Keywords:optimum design  risk  concurrent engineering  optimized evaluation point